SKW Construction Ltd
OLD FLETTON PRIMARY SCHOOL
Client -
Peterborough Town Council
​
​
​
Building use -
Classroom
​
​
Procurement Method -
Purchase only.
​
​
Procurement Duration -
​
7 weeks.
​
The SOLUTION
The 1 bay 8m x 3m building was required to provide additional space for the school which accommodates over 400 students as a stimulating space to allow focus for children who required 1 to 1 teaching. The room consists of a retractable, sound proofed, soft room divider at request of the client, so that the room can be separated and create two separate classrooms when required.
To compliment the façade of the old school building, cedar cladding was added to the new building whilst onsite to allow the building to create seamless harmony. This method of externally cladding onsite, had no impact on programme or price, evidencing that we have zero compromises on quality when it comes to the overall results of the building.